Case Study: Design, manufacture and erection of a 2 storey steel framed building
Design, manufacture and erection of a 2 storey steel framed building with fully decked first floor, windows, doors and flashings.
Erection of a two storey single flight building on foundations provided by others. Decking of first floor with 38 mm HDPB for office loading, all finishing flashings around doors and windows.
Services Supplied By McCanns:
Steel frame design, manufacture of all steelwork and flashings, erection of steelwork, cladding and flashings.
Project Value:
£400,000.00
The building had to be manufactured and shipped to Guernsey on a very tight lead time. The site was an existing working site with very limited working or storage area for materials.
McCanns transported all plant necessary for the contract to Guernsey with all materials and completed the works in 14 days.
McCanns transported all plant necessary for the contract to Guernsey with all materials and completed the works in 14 days.
Case Studies
- Design, manufacture and erection of a 2 storey steel framed building
- Design, manufacture & erection of a complex shaped steel framed building on a slab and basement (by others).
- Design, manufacture and erection of a 140 m². two storey steel framed extension to an existing warehouse unit to form a first floor office area with reception and car parking at ground floor.
- Design, manufacture & erection of extension to an existing, manufacturing and storage facility